Objective 2.1

CC

Understand business continuity (BC).

Objective 2.1 sits in Business Continuity, DR, and Incident Response, which carries 10% of the Certified in Cybersecurity exam. The questions below are original, written from the official objective title above, and each explanation cites the ISC2 page it rests on.

Objective title verbatim from the official objectives. ISC2 exam page ↗

A worked example

Shown solved, with the whole explanation open: this is what every question here carries.

2-1Business Continuity, DR, and Incident Response

What is the purpose of a business continuity plan?

Prosecuting attackers after a breachLegal pursuit of attackers is a separate track and never the plan's job.
Replacing the need for insuranceInsurance transfers financial risk; it cannot run the business for you.
Advertising resilience to customersA plan may reassure customers, though that is a side effect.
Managing operations through a disruptionCorrect · your answerCorrect. The plan exists to keep the business running through a disruption.

Correct.

Checked against ready.gov, August 2026

Concept

Continuity planning accepts that disruptions will happen and prepares the organization to keep functioning through them, rather than trying to prevent every cause.

Why D

Ready.gov frames it directly: organize a continuity team and compile a business continuity plan to manage a business disruption.

Source

Organize a business continuity team and compile a business continuity plan to manage a business disruption.

Ready.gov, Business Continuity Planning, checked August 2026
#business-continuity#bcp

Now you: objective 2.1 questions

No account needed. The explanation opens when you answer.

Sample question 1 of 3

2-1Business Continuity, DR, and Incident Response

Before choosing continuity strategies, a team must learn which functions cost the most when interrupted. Which analysis provides that?

Sample question 2 of 3

2-1Business Continuity, DR, and Incident Response

A flood shuts the head office and the company must run at partial capacity for two weeks. You are writing the business impact analysis that will guide that period. What must it identify?

Sample question 3 of 3

2-1Business Continuity, DR, and Incident Response

A flood halts your company's plant. Which processes does the BIA report say to restore first?

Full Certified in Cybersecurity question bank coming

We’re writing the complete bank from the official objectives right now. Leave your email and we’ll tell you when it ships, nothing else, ever.

Read the sources

These are the official pages the questions above cite. Reading them is studying the objective from the primary source, which is what the explanations point you toward anyway.

More objectives in Business Continuity, DR, and Incident Response